Mark Needham

Thoughts on Software Development

The transparency of Agile

with 4 comments

One of the key ideas behind agile software development is providing information as early as possible to allow the business to best make decisions.

There are a variety of ways that this is done including the use of burn up charts, estimates of scope and velocity for example. This data is compiled to try and give an accurate idea of how long a project is likely to take so that the business can work out early on whether the value it adds is worth the expected cost.

I strongly believe in this approach, certainly favouring it over other approaches that I used before working at ThoughtWorks. However, over the last couple of months I have started to wonder whether providing the business with this information so straight up actually works against you.

I believe the way that the information is viewed is different depending on when it is provided.

For example, if you have a piece of work which is due to take 12 weeks and you work out after 3 weeks that based on the current velocity it is likely to take 14 weeks you are in a weaker position than if you keep this information to yourself and then ask for another two weeks when you get to the 12 week mark.

From the business' perspective I suppose it makes sense – if after 3 weeks you're already 2 weeks behind then who knows how far you will be behind after 14 weeks.

I am not suggesting that it's better to hold back this information but surely there has to be a better way to present it because from what I've seen the baseline figure is what's looked at and the details are ignored.

Nor am I advocating that we under estimate on purpose to get the baseline figure lower. Clearly you will end up ruining your delivery reputation if you consistently over promise and under deliver.

The driver behind the agile approach is to always add business value, and while as a developer I would prefer to try and provide something to the client, as Mark points out, it has become clear to me that maybe sometimes cancellation is the best way of doing this.

Share and Enjoy:
  • Digg
  • del.icio.us
  • Facebook
  • HackerNews
  • StumbleUpon
  • Twitter

Written by Mark Needham

August 26th, 2008 at 11:46 am

Posted in Agile

Tagged with ,

4 Responses to 'The transparency of Agile'

Subscribe to comments with RSS or TrackBack to 'The transparency of Agile'.

  1. [...] touched earlier on the transparency of agile and I've been thinking about some of the ways that we track/report [...]

  2. [...] to afford to do the project if the estimates are too far removed from what they are expecting. As I mentioned earlier this up front transparency may in fact be in the best interests of the client even if it doesn't [...]

  3. [...] to bad news was something else which was pointed out as being fairly important and it's certainly an area where we often run into trouble – often organisations aren't used to bad news being delivered to them early and they get the [...]

  4. [...] transparency and visibility that we typically have when following a more agile approach was mentioned by a couple of the [...]

Leave a Reply